For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Concrete slabs have been poured to all terraces & the communal building;
  • Structural timber framing is complete for buildings 10, 6, 9, 5, 8 & the communal building;
  • Lower frames have been stood for buildings 4 & 7 & 11;
  • Roof has been installed to buildings 6, 10, 5 & 9;
  • Plumbing electrical & air-conditioning rough-in are complete to buildings 10 & 6;
  • External cladding & hebel is complete for building 6 and is underway to buildings 10 & 9;
  • Internal plasterboard sheeting is near complete to building 6.

We look forward to bringing you more updates as Topia Edition comes to life.