For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Structural timber framing is near complete to all buildings;
- Roof has been installed to buildings 4 to 10;
- Plumbing electrical & air-conditioning rough-in is near complete to buildings 4 to 10;
- External cladding & hebel is complete for buildings 5 to 10;
- Render complete on buildings 5, 6, 9 and 10;
- Internal plasterboard sheeting is complete to buildings 5 to 10;
- External painting in near complete for buildings 6 and 10 and is underway to buildings 5, 8 & 9;
- Tiling is near complete for buildings 6 and 10;
- First kitchens and vanities have been installed to buildings 6 with building 10 underway;
- Internal painting is underway to buildings 6 and 10;
- External window hoods have been installed to buildings 6 and 10 with scaffold now removed.