For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Structural timber framing is complete to all buildings;
  • Roofs have been installed to all buildings;
  • Plumbing electrical & air-conditioning rough in is near complete to all buildings;
  • External cladding & hebel is complete for buildings 4 to 12, with render complete on buildings 4 to 10;
  • Internal plasterboard sheeting is complete to buildings 4 to 10, 12 & 13;
  • External painting in near complete for buildings 4 to 10;
  • Tiling is near complete for buildings 4 to 10;
  • Kitchens and vanities have been installed to buildings 5 to 10, with appliances installed to buildings 6 & 10.
  • Internal painting is underway to buildings 4 to 10;
  • External window hoods have been installed to buildings 4 to 10 with scaffold now removed;
  • Plumbing and electrical fit is near complete to buildings 6 & 10;
  • Courtyard dividing fences and landscaping has commend to building 4 to 10.

We look forward to bringing you the final update for Topia Edition.