For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Bulk earthworks and retaining walls are complete;
  • Civil stormwater and sewer is complete;
  • Electrical and communications underground mains have been installed throughout the site;
  • External electrical Energex conduits have been installed;
  • Under slab plumbing has been complete to all buildings;
  • Road kerbs and gravels have been installed with chip seal down;
  • Concrete building slabs are due to commence in the coming weeks.