For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Timber frames are essentially complete to all buildings;
  • Roofing has been installed to buildings 2 to 5;
  • Plumbing & electrical rough-ins are complete to buildings 2, 3 & 4 & are underway for building 5;
  • External cladding is complete for buildings 2, 3 & 4 and is underway on building 5 with render near complete on buildings 2 & 3;
  • Internal plasterboard sheeting is complete for buildings 2 & 3 and is underway in building 4;
  • Internal tiling is complete in building 2 and is underway in building 3;
  • Plumbing, electrical and air-conditioning fit off is underway in building 2;
  • External painting is near complete on building 2 with internal painting underway in building 2 & 3.