For those interested in the facts and figures, below is a list of construction achievements for this month:
- Tiling is 20% complete;
- Roofing is 80% complete;
- Brickwork is 85% complete;
- External cladding is 75% complete;
- Ceilings and linings are 70% complete;
- Electrical and plumbing fit offs have commenced in buildings 15, 16 and 17;
- Fixed joinery is 20% complete;
- Rear patio installations have commenced;
- External landscaping has commenced to buildings 15, 16 and 17.