Welcome to the construction update for Saville by Azure. We are pleased to share the recent developments and accomplishments from the past month.
One of the significant achievements in the past month includes the completion of roofing for Buildings 3, 4, and 5.
We are excited to announce that the final concrete slab for Saville has now been poured. This marks a crucial stage in the construction process.
The blockwork for the communal area has been successfully finished, enhancing the functionality and aesthetics of the space.
Key highlights for the month include the commencement of internal plasterboard sheeting in Buildings 3 and 4. This marks the transition to the interior finishing phase, adding the finishing touches to these residences.
Additionally, the cladding process for Buildings 2, 4, and 5 is currently underway, enhancing the exterior of these buildings and progressing toward their completion.
At Saville by Azure, we remain committed to delivering excellence. We are dedicated to creating a truly exceptional living experience, and we look forward to sharing more exciting updates as we continue to shape these exceptional residences.