We are pleased to provide you with the construction update for August 2024.

The main retaining wall is complete and is ready for backfilling. Earthworks have reached 85% completion, marking significant progress on-site.

The installation of the 69KL sewer storage tanks is underway, and the pad footings for the suspended deck have commenced.

Looking ahead, underground services are set to begin in September.

We look forward to bringing you more updates as Elwood by Azure comes to life.