For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Civil works are essentially complete including services throughout the site;
  • Plumbing and electrical under slab services have been complete to all buildings;
  • Concrete slabs have been poured for buildings 2 to 6 and half of building 7;
  • Timber frames have been installed for buildings 2 & 3 and are underway on building 4;
  • Roofing has been installed to building 2;
  • Plumbing and electrical rough-ins have commenced on building 2;
  • External cladding is ready to commence for building 2.