For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Site strip completed with bulk earthworks nearing completion;
  • Retaining walls are 60% complete with the majority of building pads cut to earthworks level;
  • Internal road box-out has been cut to subgrade level and passed Geotech testing.

We look forward to bringing you more updates as Dawn Edition comes to life.