For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Bulk earthworks and retaining walls are complete;
- Civil stormwater and sewer is complete;
- Electrical and communications underground mains have been installed throughout the site;
- External electrical Energex conduits have been installed;
- Under slab plumbing has been complete to all buildings;
- Road kerbs and gravels have been installed with chip seal down;
- Concrete building slabs are due to commence in the coming weeks.