The Alton II Edition October Construction Update 

We are excited to announce that construction at Alton Edition is continuing to progress well and are on program to settle in quarter one 2019. During October all of the main service connections were completed throughout the development.

Building 1 – 4 (TH’s 59 – 74)
Buildings 1 – 4 have progressed well with all underground services are compete with all slabs due to be complete in November. Wall framing has commenced and services connections are underway with the external cladding, rendering and painting tracking well creating the architectural features. Internally plasterboard sheeting is ongoing with kitchen installation commenced.

Building 5 – 8 & 10 (TH’s 75 – 98)
Buildings 5-8 are more progressed than buildings 1 -4. External cladding, rendering and painting has been completed on these terraces with preparation underway for pathways, roads and landscaping. The internal finishes are progressing with kitchens and stone benchtops install complete. During November the terraces will see the continuation of floor finishes and internal painting.

Building 9 & 11 – 14 (TH’s 93, 94 & 99 – 118)
Buildings 9 & 11 – 14 are the most progressed terraces. Final touches are currently being carried out. All footpaths and roads have been poured with landscape works well advanced and due to be complete during November. Internally trades are finalising the townhouses and placing finishing touches.