The Alton III Edition April Construction Update

Azure is pleased to advise that practical completion of the Alton Edition Stage 3 is anticipated in July and accordingly, we will be in touch with you in due course regarding your settlement.

Building 1 & 2 (TH 119 – 125) 
Buildings 1 & 2 are close to completion. Scaffolding has now been removed and rendering and painting have been completed. The kitchens are complete with installation of stone bench tops. The final paint is underway and floor coverings and robes have been installed.

Building 3 & 4 (TH 126 – 133)
External cladding, rendering and painting is complete with the scaffolding now removed courtyard fencing and patio roofs are underway. Internally plasterboard wall and ceiling sheeting and carpentry fix out is complete with internal painting ongoing and kitchen installation underway.

Building 5 & 6 (TH 134 – 141)
External cladding, rendering and painting is complete with the scaffolding now removed. Internally electrical and plumbing services have been installed with plasterboard sheeting complete and first coat of paint underway. Preparation is underway for the internal concrete road between building 5 and 6.

Building 7 (TH 142 – 154)  
External cladding, rendering and painting is complete with the scaffolding now removed. Electrical and plumbing services have been installed and plasterboard sheeting is complete ready for first coat of paint.

Building 8 & 9 (TH’s 146 – 153) 
There has been great movement this month, scaffolding has now been removed and rendering and painting have been completed. The kitchens are complete with installation of stone bench tops. The final paint is underway and floor coverings and robes have been installed.