The Alton ll Edition September Construction Update 

We are excited to announce that construction at The Alton Edition is continuing to progress well. The construction schedule for The Alton Edition is still progressing to finish quarter two 2019.

Communal Areas

  • Bulk earthworks are complete;
  • In-ground services are complete (water, sewer, SW, electrical conduits);
  • Storm water detention tank is complete;
  • Internal roadways have commenced with first roads poured;

Terrace 1 -2 (59 – 74)

  • Underground services are complete;
  • Bored piers are complete;
  • 75% of the slab on ground have been poured;
  • Wall framing is 50% complete;

Terrace 3-4  (59 – 74)

  • Underground services are complete;
  • Bored piers are complete;
  • Slab on ground is near complete;
  • Wall framing is near complete;
  • Services rough in has commenced;
  • External cladding is underway;
  • Rendering has commenced;

Terrace 5-7 (75-88)

  • Scaffold has been removed;
  • External cladding is underway;
  • Services rough- in has commenced;
  • Rendering is complete and external painting is complete;
  • Plasterboard sheeting is complete;
  • Carpentry fix out is complete;
  • Kitchen joinery is installed;
  • Internal painting is near complete;

Terrace 8 & 10 (89 -98)

  • Scaffold is fully erected;
  • Windows have been installed;
  • Roof sheeting has been installed;
  • External cladding is complete;
  • Rendering is complete;
  • Services rough-in is complete;
  • Plasterboard sheeting is complete;

Terrace 9 (93 -106)

  • Rendering is complete and external painting is complete;
  • Plasterboard sheeting is complete;
  • Carpentry fix out is complete;
  • Kitchen joinery and benchtops have been installed;
  • Tiling is complete;
  • Electrical and plumbing fit off is complete;
  • Internal painting is near complete;
  • Shower screens and robes are installed;

 Terrace 11 (99 -102)

  • Rendering is complete and external painting is complete;
  • Plasterboard sheeting is complete;
  • Carpentry fix out is complete;
  • Kitchen joinery and benchtops have been installed;
  • Tiling is complete;
  • Electrical and plumbing fit off is complete;
  • Internal painting is complete;
  • Shower screens and robes are installed;

Terrace 12 (107 -110)

  • Works are essentially complete with final touches being completed and external landscaping underway;

Terrace 13 & 14 (111 -118)

  • Works are essentially complete with final touches being completed and external landscaping underway