The Emerson Edition September Construction Update

We are excited to announce that construction at The Emerson Edition is continuing to progress well. The construction schedule for The Emerson Edition is still progressing to finish quarter two 2019. 

Communal Areas

  • Site Establishment is complete;
  • Bulk earthworks complete;
  • In ground hydraulic and civil services are essentially complete ;
  • Western boundary retaining wall is complete;
  • Western boundary fencing is complete;
  • Eastern Entry statement masonry wall has been constructed;
  • Site main water meter and internal reticulation is installed and complete;
  • Site electrical reticulation pit and pipe work is complete;

Terrace 1 (1 and 2)

  • Structural work of the masonry entry statement wall is complete;
  • Detailed Excavation is complete;
  • Townhouse 1 and 2 retaining walls are complete;
  • Underslab plumbing and drainage is complete;
  • Slabs are currently being prepared so they can be poured in the coming days;

Terrace 2 (3 – 8)

  • Structural masonry retaining wall is complete;
  • Patio retaining wall footings are complete;
  • Pool shells are structurally complete;
  • Slab footings piers are complete;
  • Underslab plumbing is complete;
  • Slab preparation is underway;

 

Terrace 3 (9 – 13)

  • Structural masonry retaining walls are complete;
  • Patio retaining wall footings are complete;
  • Pool shells are structurally complete;
  • Slab footings piers are complete;
  • Underslab plumbing is complete;
  • Lower and upper slabs have now been poured;
  • Structural steel is currently being erected;

Terrace 4 (14 and 15)

  • Structural masonry retaining walls are complete;
  • Pool shells are structurally complete;
  • Patio retaining wall footings are complete;
  • Under slab plumbing is complete;
  • Lower and upper slabs have now been poured;
  • Structural steel work is complete;
  • Wall and floor framing is underway