The Emerson Edition October Construction Update 

Construction over the past month at The Emerson Edition has been progressing to schedule even with the wet weather events. Construction is scheduled to finish in quarter two 2019.

Building 4 (Terrace 14 and 15)
Terrace 14 & 15 are the most advance in the development program, all structural steel has been installed and wall and floor framing has started and will continue through November.Scaffolding was completed in October which will allow roof trusses to be installed in November.

Building 2& 3 (Terrace 3 – 13)
Terrace 9 -13 are progressing well and have had all of the structural steel installed. Wall and Floor framing is currently underway and due to be completed in November. Scaffold is also currently being erected on terrace 9 – 13 with works to start on terrace 3 -8 in the coming weeks.

Building 1 (TH’s 1 and 2)
During October the slabs were poured for Terrace 1 & 2. November we will start to see walls and structural steel being installed.