The William Edition Construction Update 

November has seen lots of action onsite at William Edition. William is due for completion in late April 2019. 

Common Areas
Roadways have commenced construction and will continue to be formed over the next few months.  In ground services ( water, gas, sewer and electrical) are continuing to progress well. The shell of the pool has been poured and will continue to be worked on through December and January. 

Building 1 (TH’s 1,2,3,4 & 5)
The roof sheeting is continuing as planned and the window installation is currently underway. 

Building 2 & 3 (TH’s 6 7,8,9,10,11,12,14,16,18)
These building hare progressing extremely well all of the kitchens have been installed and internal painting is well advanced and the timber flooring has started to be installed. 

Building 4 & 5 (TH’s 13,15,17,19,21,23,25,27)
Final internal finishes are complete and timber flooring will be finished soon. The external works have started. 

Building 6 (TH’s 20, 22, 24, 26,28 ,30,32, 34)
The final internal pain has commenced, with tiling now complete. Electricity and water fit off is continuing to progress well and the timber flooring has commenced.

Building 7 (TH’s 29,31,33,35)
Building 7 is complete with defecting and cleaning are currently underway and the external works have commenced.  

Building 8 (TH’s 36,38,40 & 41)
External painting is now very advance and the kitchen joinery has begun to be installed. Doors, skirting and architraves are also being added to each of the rooms. 

Building 9 (TH’s 37 & 39)
External cladding has progressed well and is due for completion in December. Kitchens have also been installed and waterproofing is currently underway.  

Building 10 & 11 (TH’s 42, 43, 44, 45, 46, 47, 48 & 50)
Window installation has been completed with external cladding and rendering ongoing. Electrical and plumbing rough in has been completed  with plasterboard lining ongoing. 

Building 12 & 13 (TH’s 49, 51, 52 & 53)
Building 12 is starting to take shape, the upper level wall framing and roof framing is complete along with the window installation. Electrical and gas rough is has begun.