The William Edition October Construction Update 

William Edition has been progressing well in October. The weather has caused a few minor delays however construction is still due to finish in quarter two 2019.

Common Areas
Bulk earthworks have now been completed with most of the in-ground services complete. The beautiful  pool is starting to take shape with the shell  being poured.

Building 1 (TH’s 1,2,3,4 & 5)
The slabs have been poured during October with framing and roof framing complete with sheeting having commenced.

Building 2 & 3 (TH’s 6 7,8,9,10,11,12,14,16,18)
Scaffolding has been dismantled, with window and cladding installation complete.  The external terrace homes have had the render and painting compete. Internally the kitchens have been installed, tiling has been completed and the final paint has started. In building 3 tiling and flooring will be complete in November.

Building 4 & 5 (TH’s 13,15,17,19,21,23,25,27)
Final internal finishes are underway with the kitchen,  bathroom & walk in robe installation completed. Timber flooring installation is in its final stages with external works starting

Building 6 (TH’s 20, 22, 24, 26,28 ,30,32, 34)
Building 6 has completed the  initial plumbing & electric works, kitchens have also been installed. Internal painting has advanced with final service fit off and robe shelving installation underway.

Building 7 (TH’s 29,31,33,35)
Building 7 is very well advance with defect and cleaning underway. External works have started.

Building 8 (TH’s 36,38,40 & 41)
Kitchen installation has starting along with doors, skirtings and architraves. Plumbing & electric has been completed. External cladding has been finalised with rendering and painting underway. 

Building 9 (TH’s 37 & 39)
Plumbing & electrical works have been completed and the kitchen installation has started. External cladding has begun with rendering and painting due to commence in November. 

Building 10 & 11 (TH’s 42, 43, 44, 45, 46, 47, 48 & 50)
Framing has been completed and scaffold & roof sheeting has been erected. Internally electrical and plumbing services have been completed and plasterboard linings have commenced. 

Building 12 (TH’s 49 & 51)
The slabs have been poured during October with framing and roof framing complete with sheeting having commenced. Internally the plumbing and electrical service rough in has commenced. 

Building 13 (TH’s 52 & 53)
Grounds slabs have been poured and upper level wall and roof framing has been completed. Scaffolding has been erected and the service rough in has started.