Welcome to the March construction update for One Earle Lane by Azure. We're excited to share the latest developments throughout the project.
The scaffold dismantle is complete, with Levels 1 to 3 along Sylvan Road set to be reestablished next month to finalise the colonnade tiling.
Internally, wet area waterproofing, ceilings, and partition framing are now complete across Levels 1 to 9, with aluminium windows and doors at 98% completion. Fire doors and frames have reached 99%, while plasterboard sheeting is fully complete up to Level 9.
Finishing works are well advanced, with balcony tiling at 95% across Levels 2 to 8 and rooftop tiling underway at 25%. Electrical, hydraulic, and mechanical services are progressing, with the basement and lower levels nearing final fit-off completion. Fire services are now fully installed throughout, ensuring compliance and safety and readiness for the upcoming QFES Final Inspection.
Apartment finishes are taking shape, with tiling at 98%, internal painting at 95%, and joinery at 98% across Levels 1 to 8. Appliance installations have reached 90% on Levels 1 to 6, alongside shower screen and robe door installations at 75%. Carpet installation is also progressing, now at 80% completion.
In the Level 1 common areas, feature joinery cladding is at 75% and tiling works are now 85% complete.
Externally, rendering is 95% complete, with external painting, including soffits, nearing final stages at 98%. Balustrade installation is now fully complete, and metalwork screen installation is at 90%.
Colonnade cladding continues, now 65% finished. The rooftop is also taking shape, with Level 9 fit-out works, including plasterboard linings complete and tiling, at 25%, feature cladding has commenced, while pool construction and landscaping are well advanced.
With strong momentum on-site, One Earle Lane remains on track for settlements in June 2025. As construction enters its final stages, we look forward to sharing more updates in the lead-up to completion.