One Earle Lane by Azure - Construction Update October 2024

We hope you enjoy the latest construction update for One Earle Lane by Azure.

Welcome to the October construction update for One Earle Lane by Azure. We're excited to share the latest developments throughout the project.

Currently, the scaffold dismantling for levels 7 to 10 is 75% finished, and the man and materials hoist has now been removed. The structural steel roof framing is fully complete, with roof sheeting close behind at 90%. Waterproofing works from levels 1 to the rooftop reveals are finalised, while wet area water proofing on levels 1 to 8 stands at 98% completion.

The onsite team has made significant progress on the installation front. Aluminium windows and doors from levels 1 to 8 are now 90% installed, and fire doors with frames have reached 80% completion in these same levels. Ceiling and partition framing from levels 1 to 10 are 90% done, while plasterboard sheeting for ceilings and partitions on levels 1 to 8 is 98% complete. Our main switchboard installation is fully complete, and we've reached the final stages of electrical, hydraulic, and mechanical services rough-in across key areas, with most components nearing or at 100% completion.

In interior finishes, tiling and joinery in apartments on levels 1 to 8 are progressing well, with tiling and joinery at 85%. Internal painting is at 65%, and appliance installation on levels 1 to 6 has reached 50%.

External works are also moving ahead, with render 90% complete, soffits and exterior painting at 95%, and balustrade and metalwork screen installation at 85% and90%, respectively. Lift installations are now complete, and the rubbish chute is at 85% completion.

We're thrilled to see the level 9 pool construction at 70%, adding to the extensive amenity offering for the development.

We remain on track for settlements in Quarter-1 2025and will continue to keep you informed with regular updates as One Earle Lane moves closer to completion.