Welcome to the latest construction update for One Five Six by Azure. We're excited to share the remarkable progress we've made in shaping this exceptional residential development.
Level 1's internal staircase has been successfully formed, reinforced, and poured, marking a significant accomplishment.
The Roof Terrace scaffold erection is now 100% complete, ensuring safety and accessibility for further construction activities.
Deliveries of formwork, reinforcement steel, and blockwork for Level 6 and the rooftop structures are ongoing.
Vertical concrete columns from Level 6 to the roof level are now fully formed, reinforced, and poured, enhancing the structural integrity of the building.
Blockwork walls from Level 6 to the roof level are 100% complete, adding both aesthetic appeal and functionality to the development.
The Roof Terrace slabs are now 80% complete, bringing us closer to the completion of this space.
Survey works for Level 6 and the roof terrace structure are ongoing, ensuring precision and alignment in the construction process.
Additionally, blockwork walls from Level 6 to the Roof Terrace are 100% complete, and blockwork walls to roof level structures are 50% complete, enhancing the overall structure of the building.
Temporary formwork backprops have been successfully removed from Level 2, and the removal process continues on Levels 3, 4, and 5.
In the Lower and Upper Level Basements, electrical, mechanical, and hydraulics services fit-offs are 75% complete, ensuring the provision of essential utilities.
Level 3 waterproofing to window and door reveals is 90% complete, adding protection and functionality to the building.
Aluminium and glazing installation on Levels 1 and 2 is 50% complete, while Level 3 glazing installation is 30% complete, bringing natural light into the residences.
Levels 1 and 2 have seen the completion of wall framing installation, while Level 3 is at 60% completion in this regard.
Mechanical, fire, and hydraulic services rough-in works for Level 1 are 100% complete, ensuring seamless utility provision. Meanwhile, Level 2 and 3 hydraulics services rough-in works are at 60% completion, and mechanical services rough-in works are at 15% completion.
Fire services rough-in works for Levels 1 to 5 are now 100% complete, enhancing safety provisions within the development.
Sewer and water connections have commenced, as well as the relocation of Telstra services pits in the Oxlade verge.
Building services deliveries are ongoing, ensuring the availability of essential materials for construction.
These updates reflect the dedication and progress made at One Five Six by Azure. Stay tuned for more exciting developments as we continue shaping this exceptional residential haven.