For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Concrete slabs have been poured to all terraces & the communal building;
- Structural timber framing is complete for buildings 4 to 10 & the communal building;
- Lower frames have been stood for buildings 2, 3, 11, 12, 13;
- Roof has been installed to buildings 4 to 10;
- Plumbing electrical & air-conditioning rough-in are near complete to buildings 4, 5, 6, 10;
- External cladding & Hebel is complete for buildings 6, 10 & 9;
- Render complete on buildings 6 & 10;
- Internal plasterboard sheeting is complete to buildings 6 & 10;
- External painting is underway for buildings 6 & 10;
- First kitchens and fit off are due to be installed in the coming month.
We look forward to bringing you more updates as Topia Edition comes to life.