For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Structural timber framing is complete to all buildings;
- Roofs have been installed to all buildings;
- Plumbing electrical & air-conditioning rough in is near complete to all buildings;
- External cladding & hebel is complete for buildings 4 to 12, with render complete on buildings 4 to 10;
- Internal plasterboard sheeting is complete to buildings 4 to 10, 12 & 13;
- External painting in near complete for buildings 4 to 10;
- Tiling is near complete for buildings 4 to 10;
- Kitchens and vanities have been installed to buildings 5 to 10, with appliances installed to buildings 6 & 10.
- Internal painting is underway to buildings 4 to 10;
- External window hoods have been installed to buildings 4 to 10 with scaffold now removed;
- Plumbing and electrical fit is near complete to buildings 6 & 10;
- Courtyard dividing fences and landscaping has commend to building 4 to 10.
We look forward to bringing you the final update for Topia Edition.