For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Plumbing electrical & air-conditioning rough in is complete to all buildings;
  • External cladding & hebel is near complete to all buildings;
  • Internal plasterboard sheeting is complete to all buildings;
  • External painting in near complete for buildings 4 to 10, 12 & 13;
  • Tiling is near complete for buildings 4 to 10, 12 & 13;
  • Kitchens and vanities have been installed to buildings 4 to 10, 12 & 13, with appliances installed to buildings 6 and 10;
  • Internal painting is complete to buildings 4 to 10, 12 & 13;
  • External window hoods have been installed to buildings 4 to 10 with scaffold now removed;
  • Plumbing and electrical fit off is near complete to buildings 4 to 10;
  • Courtyard dividing fences and landscaping is complete to buildings 4 to 10;
  • Carpet has been installed in buildings 6, 8, 9 & 10