For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Timber frames are complete to all buildings;
- Roofing has been installed to buildings 2 to 6;
- Plumbing and electrical rough-ins are complete to buildings 2 to 6, with fit off complete in buildings 2 & 3;
- External cladding is complete for buildings 2 to 5 and near complete on building 6;
- External painting is complete for building 2 and is underway on building 3;
- Internal plasterboard sheeting is complete for building 2 to 5 with internal painting well underway;
- Internal tiling is complete in building 2 and is underway in buildings 3 to 5;
- Kitchen joinery has been installed in buildings 2 and 3 with appliances installed;
- Carpet has been installed to half of building 2.