Welcome to the latest construction update for Willow by Azure in North Lakes. We're excited to share the progress made throughout April.
Plumbing under slabs for terraces 1 to 21 have been successfully completed, marking a significant milestone in the construction process. In addition, mains electrical reticulation has commenced for terraces 1 to 37, laying the groundwork for essential electrical infrastructure.
We're also pleased to announce that the pool shell has been completed, adding to the amenities that will enhance the community living experience at Willow.
Looking ahead, our focus will shift to internal road works, ensuring smooth access throughout the development.
We look forward to sharing more exciting developments as we continue to shape the vibrant Willow community in North Lakes.