For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Plumbing and electrical rough-ins are complete to all buildings;
- External cladding is complete for building 2 to 7 and near-complete on building 1;
- External painting and render is complete for buildings 2 to 6 and underway on building 7;
- Internal plasterboard sheeting is complete for buildings 2 to 6 and underway in building 7;
- Internal tiling is complete in buildings 2 to 6;
- Internal painting is near complete in buildings 2 to 6;
- Kitchen and bathroom joinery has been installed in buildings 2 to 6 with appliances installed;
- Plumbing, electrical and air conditioning fit off is complete in buildings 2 to 4 and underway in 5 & 6;
- Carpet has been installed to buildings 2 to 4;
- External works have commenced on the communal area with landscape prep due to commence this month.