For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Bulk earthworks and retaining walls are complete;
  • Building pads have been cut to earthworks level and internal subgrade complete;
  • Main sewer, stormwater and water underground reticulation is near complete for the site;
  • Electrical and fibre optic conduits and pits are well underway for the site;
  • Plumbing and electrical under slab services have been complete to buildings 2 and 3;
  • Concrete slabs have been poured for building 2 and 50% of building 3;
  • Timber fencing has been installed to the northern boundary and through the middle of the site.

We look forward to bringing you more updates as Dawn Edition comes to life.