For those interested in the facts and figures, below is a list of construction achievements for this month:

  • Tiling is 20% complete;
  • Roofing is 80% complete;
  • Brickwork is 85% complete;
  • External cladding is 75% complete;
  • Ceilings and linings are 70% complete;
  • Electrical and plumbing fit offs have commenced in buildings 15, 16 and 17;
  • Fixed joinery is 20% complete;
  • Rear patio installations have commenced;
  • External landscaping has commenced to buildings 15, 16 and 17.