For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • External cladding is 99% complete to building 1;
  • External render is 99% complete to building 1;
  • External paint is complete to building 7;
  • Internal tiling is complete to building 7 and near-complete to building 1;
  • Internal painting is complete to buildings 2 to 6, the final coat has been applied to building 7, and painting is underway to building 1;
  • Kitchen and bathroom joinery is underway to building 1;
  • Plumbing, electrical and air conditioning fit off is complete to buildings 2-7 and underway to building 1;
  • Carpet is being fitted in building 6;
  • External works have commenced to the communal area with landscape underway to buildings 2 - 6;
  • The final construction defect process is underway to buildings 2 and 3;
  • Road seal has commenced.