For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Concrete slabs are 100% complete to all buildings;
  • Main electrical switchboards and sub-boards are installed;
  • Timber framing is 50% complete;
  • Air conditioning, electrical and plumbing rough-ins are 10% complete;
  • Brickwork is 10% complete;
  • Lightweight cladding is 5% complete;
  • Roofing is 13% complete;
  • Filling subgrade in courtyards is substantially complete;
  • Government Road verge has been turfed. All external work to the property is now complete.