For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Bulk earthworks, road box out and all retaining walls are now complete;
- Building pads are cut to level with screw piers installed;
- Stormwater detention tank has been constructed and back filled;
- Civil stormwater and sewer is complete;
- Electrical underground mains have been installed to 60% of the site;
- External electrical Energex conduits have been installed with main water lead in complete;
- Under slab plumbing has been complete to 3 buildings.
We look forward to bringing you more updates as Flora Edition comes to life.