For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Main sewer, stormwater and water underground reticulation are complete for the site;
  • Electrical and fibre optic conduits and pits are complete;
  • Plumbing and electrical under slab services have been completed to buildings 2 & 4 and are underway for building 5;
  • Concrete slabs have been poured for buildings 2 & 3;
  • Timber frames have been installed for building 2 and are underway for building 3.

We look forward to bringing you more updates as Dawn Edition comes to life.