For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Bulk earthworks, road box out and all retaining walls are now complete;
  • Building pads are cut to level with screw piers installed;
  • Stormwater detention tank has been constructed and back filled;
  • Civil stormwater and sewer is complete;
  • Electrical underground mains have been installed to 60% of the site;
  • External electrical Energex conduits have been installed with main water lead in complete;
  • Under slab plumbing has been complete to 3 buildings.

We look forward to bringing you more updates as Flora Edition comes to life.