For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Bulk earthworks and road box out have been completed with retaining walls near complete;
  • Building pads are cut to level with piers ready to commence;
  • Stormwater detention tank has been constructed and back filled;
  • Civil stormwater is complete with sewer 50% complete;
  • External electrical Energex conduits have been installed with main water lead in near complete;
  • Swimming pool concrete shell has been poured.

We look forward to bringing you more updates as Flora Edition comes to life.