For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Electrical and communications underground mains have been installed throughout the site;
- External electrical Energex conduits have been installed;
- Main switchboard and sub-boards have been installed throughout the site;
- Internal roadway gravels and kerbs are complete;
- Concrete building slabs are now complete;
- Castamore Way road widening works are complete;
- Timber framing is due to commence this month.