For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Plumbing electrical & air-conditioning rough in is complete to all buildings;
- External cladding & hebel is near complete to all buildings;
- Internal plasterboard sheeting is complete to all buildings;
- External painting in near complete for buildings 4 to 10, 12 & 13;
- Tiling is near complete for buildings 4 to 10, 12 & 13;
- Kitchens and vanities have been installed to buildings 4 to 10, 12 & 13, with appliances installed to buildings 6 and 10;
- Internal painting is complete to buildings 4 to 10, 12 & 13;
- External window hoods have been installed to buildings 4 to 10 with scaffold now removed;
- Plumbing and electrical fit off is near complete to buildings 4 to 10;
- Courtyard dividing fences and landscaping is complete to buildings 4 to 10;
- Carpet has been installed in buildings 6, 8, 9 & 10