Welcome to the latest construction update for Willow by Azure in North Lakes.
June has been a productive month across the site. The concrete slabs for terraces 1 to 21 are complete, and the slabs for terraces 22 to 37 are over 50% finished.
We have begun work on the piers for the slabs of terraces 57 to 69, and the two-tier retaining wall behind these terraces is underway. Additionally, stormwater drainage under the road behind terraces 57 to 69 has commenced.
Looking ahead, we aim to complete the slabs for terraces 22 to 37 and begin the slabs for terraces 38 to 42. The piers for the slabs of terraces 57 to 69 will be completed, and the retaining wall behind these terraces will be finished.
We look forward to sharing more exciting developments as we continue to shape the vibrant Willow community in North Lakes.