For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- External cladding is 99% complete to building 1;
- External render is 99% complete to building 1;
- External paint is complete to building 7;
- Internal tiling is complete to building 7 and near-complete to building 1;
- Internal painting is complete to buildings 2 to 6, the final coat has been applied to building 7, and painting is underway to building 1;
- Kitchen and bathroom joinery is underway to building 1;
- Plumbing, electrical and air conditioning fit off is complete to buildings 2-7 and underway to building 1;
- Carpet is being fitted in building 6;
- External works have commenced to the communal area with landscape underway to buildings 2 - 6;
- The final construction defect process is underway to buildings 2 and 3;
- Road seal has commenced.