For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Cladding is near complete on building 1;
- External render is near complete on building 1;
- External paint is underway to building 7;
- Internal plasterboard sheeting and setting is now complete;
- Internal tiling is well underway to buildings 1 & 7;
- Internal painting is complete to buildings 2 & 3, and near complete to buildings 4 to 7;
- Kitchen and bathroom joinery has been installed to buildings 7;
- Plumbing, electrical & air conditioning fit off is complete to buildings 2 to 4, near complete on buildings 5 to 6, and underway to building 7;
- Carpet has been installed to buildings 2 to 5;
- External works have commenced to the communal area with landscape underway to buildings 2, 3 & 4;
- Final construction defect process started to buildings 2 & 3.