For those of you interested in the facts and figures below is a list of construction deliverables for your reference:

  • Concrete slabs have been poured for all buildings;
  • Main electrical switchboards are installed;
  • The roof has been installed to building 11, with external wall cladding and brickwork commencing shortly;
  • Wall and roof framing is 95% complete to buildings 8 & 9 and is underway on buildings 6, 7 & 12.