For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Concrete slabs are 100% complete to all buildings;
- Main electrical switchboards and sub-boards are installed;
- Timber framing is 50% complete;
- Air conditioning, electrical and plumbing rough-ins are 10% complete;
- Brickwork is 10% complete;
- Lightweight cladding is 5% complete;
- Roofing is 13% complete;
- Filling subgrade in courtyards is substantially complete;
- Government Road verge has been turfed. All external work to the property is now complete.