For those of you interested in the facts and figures below is a list of construction deliverables for your reference:
- Concrete slabs have been poured for all buildings;
- Main electrical switchboards are installed;
- The roof has been installed to building 11, with external wall cladding and brickwork commencing shortly;
- Wall and roof framing is 95% complete to buildings 8 & 9 and is underway on buildings 6, 7 & 12.